Case Study: Use Case of WFP (The Early Days)
Project Overview EdmontonApproximately $500 Million2007 Project Summary: Mandated by the Contractor, not the Owner. Key Results: Pipe installed at 2.6 hours per foot.(Other contractor, …
Project Overview EdmontonApproximately $500 Million2007 Project Summary: Mandated by the Contractor, not the Owner. Key Results: Pipe installed at 2.6 hours per foot.(Other contractor, …
Project Overview Workface Planning – Mid-Project ReportFort McMurrayApproximately $2 Billion2007-2010 Project Summary: Both Client and the Contractor have experience with WFP The Project-B has …
Project Overview Workface Planning – Mid-Project ReportToledo OhioApproximately $500 Million2008 Project Summary: WFP established by the Contractor, Owner has no experience with WFP The …
Project Overview North Vancouver, Canada$300 Million2009 WFP applied by the Contractor, Owner and CMT have no experience with WFP. Key Outcome: Contractor was given …
Project Overview Series of sustaining projectsFort McMurray, Alberta$300 Million40-day shutdown with pre-shutdown scope. Key Outcome: Completed one day early with a perfect safety record. …
Project Overview Series of sustaining projectsFort McMurray, Alberta$300 Million annual budgetOctober 10th – 22nd 2011 Scope: Optimize the execution process of construction through the …
Project Overview Fort McMurray, AlbertaApproximate TIC $1.8 BillionDec 10 2013 Assessment Deliverables A review of the general construction contractor’s WFP Procedure highlighting its strengths …
Executive Overview Company D (the Owner) is one of the largest producers of crude oil from Canada’s oil sands. It operates a large oil …
Audit of Workface Planning – Mid project $5 Billion Peace River, Canada 2015 Audit process: This audit tool has been developed to support the …
Workface Planning Review and Scorecard Audit Notes and Recommendations Redwater, Alberta$750 Million2015 Mid project review: for the purpose of developing a company standard for …