- Case Study: Use Case of WFP (The Early Days)Project Overview EdmontonApproximately $500 Million2007 Project Summary: Mandated by the Contractor, not the Owner. Key Results: Pipe installed at 2.6 hours per foot.(Other contractor, not …
- Case Study: Lessons Learned – Mid Project ReviewProject Overview Workface Planning – Mid-Project ReportFort McMurrayApproximately $2 Billion2007-2010 Project Summary: Both Client and the Contractor have experience with WFP The Project-B has seen …
- Case Study: WFP Mid-Project ReportProject Overview Workface Planning – Mid-Project ReportToledo OhioApproximately $500 Million2008 Project Summary: WFP established by the Contractor, Owner has no experience with WFP The following …
- Case Study: WFP Review & Recommendations for OptimizationProject Overview North Vancouver, Canada$300 Million2009 WFP applied by the Contractor, Owner and CMT have no experience with WFP. Key Outcome: Contractor was given permission …
- Case Study: 40 Day Shutdown and Pre-shutdown ScopeProject Overview Series of sustaining projectsFort McMurray, Alberta$300 Million40-day shutdown with pre-shutdown scope. Key Outcome: Completed one day early with a perfect safety record. Project …
- Case Study: Optimizing WFP ExecutionProject Overview Series of sustaining projectsFort McMurray, Alberta$300 Million annual budgetOctober 10th – 22nd 2011 Scope: Optimize the execution process of construction through the application …
- Case Study: Assessment of WFP Procedures and RecommendationsProject Overview Fort McMurray, AlbertaApproximate TIC $1.8 BillionDec 10 2013 Assessment Deliverables A review of the general construction contractor’s WFP Procedure highlighting its strengths and …
- Case Study: Impact of AWP Methodology on Project ExecutionExecutive Overview Company D (the Owner) is one of the largest producers of crude oil from Canada’s oil sands. It operates a large oil sand …
- Case Study: WFP Audit Processes and FindingsAudit of Workface Planning – Mid project $5 Billion Peace River, Canada 2015 Audit process: This audit tool has been developed to support the evaluation …
- Case Study: Mid-Project WFP ReviewWorkface Planning Review and Scorecard Audit Notes and Recommendations Redwater, Alberta$750 Million2015 Mid project review: for the purpose of developing a company standard for WFP. …
- Case Study: WFP Planning ScorecardMid-project reviewFort McMurray, Canada$1 Billion2015 Workface Planning Scorecard Summary The review was conducted onsite by Insight-AWP utilizing the methodology and structure contained in the Workface …
- Case Study: Insight-AWP Partners with Bentley and Wins!PROJECT L:New construction, $450 million.Houston, USA2016End of project summaryWinner of the ‘Be Inspired’ award from Bentley. Changing Minds and Paradigms The Challenge: In November 2014 …
- Case Study: AWP Readiness for Execution$1 BillionAWP Field Mobilization Readiness Review2016 At the request of our client, Insight-AWP conducted a cold eyes project review of Project-M in late 2016. The …
- Case Study: Productivity AuditProject-NRedwater, Alberta$5 Billion5000 CraftworkersStudy period: February 2016 – September 2016 Insight‐AWP has been involved in the examination and management of productivity on mega projects since 1998 …